Project Status & What to Expect This Week
Updated Nov. 27
Demolition of the former Eastern Gateway building is scheduled to officially begin Nov. 30. The initial phase will focus on clearing the interior of the building, with heavy demolition of the structure scheduled to begin in January 2027.
- South Champion St. - Closed to vehicles and pedestrians
- South Walnut St. - Open to northbound traffic only; sidewalk open on the east side only
- East Federal St. - Open to vehicles; sidewalk open on the north side only
- East Boardman St. - Open to vehicles; sidewalk open on the south side only
Schedule is subject to change. This section is updated weekly.
Project Timeline
- PlanningJun–Aug 2026
- ProcurementSep–Oct 2026
- DemolitionNov 2026–Apr 2027We are here
- ConstructionSep 2027
- OpeningEarly 2029
Project Overview
Mahoning County and the Western Reserve Port Authority are partnering to transform a close to 2-acre site, home to a non-functioning building and parking deck, into a state-of-the-art government center all residents can be proud of. The roughly $60 million investment right-sizes county facilities and centralizes most departments to strengthen public service delivery.
Better constituent services
- Consolidates core county services now spread across multiple sites
- Improves accessibility for residents
- Lowers long-term maintenance and operating costs tied to Oak Hill and other aging facilities
Economic growth
- Creates a gateway to the county's economic development ecosystem and a “one-stop” for prospects
- Brings hundreds of employees downtown, increasing foot traffic for local businesses
- Keeps a key downtown property active and productive
Parking & downtown impact
- New 300+ space deck serves government center visitors and downtown patrons
- Brings activity downtown, supporting local businesses and investment
Frequently Asked Questions
Demolition, construction and downtown impacts
Will there be street closures during the construction?
South Champion St. will be closed to vehicles with sidewalks limited to the west side. East Federal St. and East Boardman St. stay open to vehicles, with sidewalks limited to one side. South Walnut St. will be open to northbound traffic only, with the sidewalk open on the east side. Truck traffic will be routed out away from downtown's main commercial corridors.
How will demolition and construction affect downtown businesses?
Downtown will remain open throughout the project. Work will stay within the site footprint, truck traffic will be routed out of downtown, and any street or sidewalk closures will be limited and posted in advance. The project team will stay in regular contact with residents and business owners to keep disruption to a minimum.
Once the government center opens, it will bring hundreds of employees and visitors downtown each day, adding foot traffic for nearby shops and restaurants.
What is being done to control dust, noise and debris?
Demolition follows a dust and stormwater control plan based on standard best practices, including water suppression, perimeter controls and street cleaning. Fencing, signage and safety perimeters will guide people around the work zone, and a dedicated contact line will be available for concerns.
Will the project reduce downtown parking?
No working parking is being lost. The former Eastern Gateway parking deck has been closed since April 2025. The new government center will include a new deck with 300+ spaces for visitors and employees and will be open to the public after hours for downtown events and businesses.
Location and site
Why downtown Youngstown?
Youngstown is the county seat. Locating the government center near the County's economic development and service partners creates a government services and economic development corridor.
Why demolish the Eastern Gateway building instead of reusing it?
The former Eastern Gateway Community College building and its parking deck are no longer usable. The deck has been closed since April 2025 for safety and usability reasons. Clearing the nearly 2-acre site lets the County build a facility designed around residents' needs and keeps a key downtown property active rather than vacant.
What will happen to the Mocha House?
The Mocha House recently announced they are relocating to 34 W. Federal Street (the former space of West 34) in November. You can contact the Mocha House directly for their exact timeline.
Why a new government center
Why does the County need a new building? Aren't the current ones working?
Oak Hill has serious deficiencies that affect the County's ability to serve residents and add to upkeep and maintenance costs. The building has served the County for many years, but its age and layout create ongoing maintenance and accessibility problems that will cost taxpayers more over time.
Why not renovate Oak Hill?
Renovating an older building with a difficult layout would still leave the County with an aging facility, services spread across multiple sites and rising upkeep costs. A new, purpose-built center addresses those issues directly.
With so many services online, why is a physical building still needed?
Many county services still require an in-person visit, and many residents prefer or need one, including seniors and people without reliable internet access. The new center will be designed to support online services as well.
What will happen to the Oak Hill building?
The county will evaluate options for reusing, selling or redeveloping the Oak Hill site.
Planning, oversight and schedule
Why is the Western Reserve Port Authority involved, and who is accountable?
Partnering with a port authority on a project like this is a standard role under the Ohio Revised Code. It helps limit the County's financial and legal exposure while the project is under way. The County used the same process for the Mahoning County Veterans Services building last year. WRPA brings real estate and construction experience and answers to its Board of Directors; the Board of Commissioners remains accountable to voters.
What is the timeline, and how will residents know the project is on track?
The project has defined phases with posted milestone dates. Demolition of the former Eastern Gateway building is the first phase, construction is expected to begin in late 2027, and the center is targeted to open in early 2029. Residents can follow progress on the project website.
What happens if the schedule changes?
A baseline schedule is posted publicly. If anything changes, the update will note what changed and why, and progress will be shared through the project website and regular updates.
County services and access
Will county services be interrupted when offices move?
No. Residents should keep using current service locations until a move is announced. Moves will be announced well in advance, with clear instructions and information about any temporary impacts.
Which county offices will move to the new government center?
The County is reviewing which departments will relocate, with the goal of a better experience for residents. Most departments are expected to move there, and Jobs and Family Services is confirmed to be in the new building. More details will be shared in the coming months as plans are finalized.
Will the new center be accessible for seniors and people with disabilities?
Yes. Improving accessibility is one of the main goals of the project. A single, modern, ADA-compliant building, a new parking deck and clear wayfinding will be easier to use than several older sites.
Cost and funding
How much will the new government center cost, and why does it cost that much?
The project is a capital investment of roughly $60 million for a building that is expected to serve residents for decades. Today the County pays to heat, repair and staff aging buildings at several locations, and those costs keep rising. Bringing services together in one modern building is expected to lower long-term operating and maintenance costs for the county.
Will this project raise my taxes? Is there a levy planned?
No. There will be no levy for this project. It is being paid for with existing money in the County's General Fund and bonds.
Could this money be used for roads, public safety or social services instead?
The County plans to keep funding its core services while also addressing its facility needs. Building problems become more expensive the longer they are put off, and money that goes to patching older buildings is money that isn't going to services.
Will the project use union labor?
The County intends to use a Project Labor Agreement with skilled union labor. This approach supports a safe, high-quality building delivered on schedule, and it puts local tradespeople to work on a project in their own county.
Why did the County buy the InfoCision building if it planned to build a new government center?
When the County purchased the InfoCision building, the Eastern Gateway site was not available. Once it became available, building there gave the County the chance to bring most departments into one location and create a better government center at a lower overall cost.
Resources
- Public Meeting to Address Demolition, Government Center PlansBusiness Journal Daily · Oct. 23, 2026
- Public forum Wednesday on EGCC parking deck demolitionWFMJ · Oct. 23, 2026
- Port Authority Approves Contracts for Government CenterBusiness Journal Daily · Oct. 21, 2026
- Former Eastern Gateway Building Demolition to Start Next MonthBusiness Journal Daily · Oct. 6, 2026
- City committee approves demolition of former collegeThe Vindicator · Oct. 6, 2026
- November demolition slated for former Eastern Gateway parking deckWFMJ · Sept. 25, 2026
- Mahoning County Projects Could Unlock GrowthBusiness Journal Daily · May 1, 2026
- County inks agreement for demo of EGCC building to build new county government centerThe Vindicator · Jan. 22, 2026
- Commissioners, WRPA enter agreement on former Youngstown Eastern Gateway siteWFMJ · Jan. 21, 2026
- Mahoning County Commissioners approve building new government center at 101 E. Federal StreetWKBN · Jan. 20, 2026
Contact Us
Have a question or concern about the project or work near the site? Email [email protected]